US Asks Congress for $50.1 Billion to Complete Air Traffic Control Overhaul
The Takeaway: The administration wants Congress to add $50.1 billion to the $12.5 billion it has already provided for rebuilding US air traffic control. About a fifth of the new money is for control systems and telecommunications; the rest is split into equal blocks for airports, terminals, en route centers and control towers. The letter came days after a failure the FAA blames on legacy equipment led to a nationwide ground stop.
The transportation secretary, the Federal Aviation Administration (FAA) chief and the White House budget director asked Congress on Tuesday for $50.1 billion to finish replacing US air traffic control.
The joint letter, dated 17 November, is signed by Transportation Secretary Sean P. Duffy, FAA Administrator Bryan K. Bedford and Russell T. Vought, Director of the Office of Management and Budget. It is addressed to Senate Appropriations Committee Chair Susan Collins and Vice Chair Patty Murray, and to House Appropriations Committee Chairman Tom Cole and Ranking Member Rosa DeLauro.
The FAA “needs Congress to accelerate further investment in the National Airspace System,” the letter says. The new system, it adds, will require significant infrastructure work, including new Air Route Traffic Control Centers, the regional facilities that handle aircraft between airports, and Airport Traffic Control Towers. The $50.1 billion is a request for Congress to appropriate, not money already approved, and the letter sets no deadline for a decision.
Five lines, four of them worth $10 billion each
The biggest single item sits inside the modernization line. Air traffic control modernization, at $10.1 billion, includes $7.2 billion for a common automation platform and common controller workstations.
The rest of that line is $2 billion for cloud computing and national airspace system telecommunications and $600 million for strategic air traffic flow management technologies. Another $300 million would consolidate terminal air traffic control facilities.
The automation platform alone accounts for 71.3% of the line and 14.4% of the whole request.
The four other lines are $10 billion each. Airport infrastructure splits evenly between $5 billion of discretionary grants under the Airport Improvement Program and $5 billion under the Airport Terminal Program.
A separate $10 billion Terminal Pilot Program would fund the replacement, modernization or full reconstruction of aging terminals at high-impact transitional hub airports.
The Air Route Traffic Control Centers line covers the design, site selection, land acquisition and construction of up to five new consolidated centers. The letter says they would replace legacy centers from the 1960s that are beyond their service life.
The department’s release puts the current number of centers at 22 and says the last was built in 1969.
The last $10 billion is for the construction, replacement and improvement of up to 140 FAA-owned air traffic control towers.
Spread evenly across the maximum counts, the tower line averages about $71.4 million a tower and the center line $2 billion a center. These are illustrative averages, not budgets the letter sets for any project.
The request by line (in $ billions; share in %)
| Line | Amount | Share |
|---|---|---|
| Air traffic control modernization | 10.1 | 20.2 |
| Airport infrastructure | 10.0 | 20.0 |
| Terminal Pilot Program | 10.0 | 20.0 |
| Air Route Traffic Control Centers | 10.0 | 20.0 |
| Air traffic control towers | 10.0 | 20.0 |
| Total | 50.1 | 100.0 |
Shares are The Edge’s calculations and do not sum to 100 because of rounding.
Inside the modernization line (in $ millions)
| Item | Amount |
|---|---|
| Common automation platform and controller workstations | 7,200 |
| Cloud computing and airspace telecommunications | 2,000 |
| Strategic air traffic flow management | 600 |
| Consolidation of terminal control facilities | 300 |
| Total | 10,100 |
The $12.5 billion already provided is fully allocated
The request comes on top of $12.5 billion from the Working Families Tax Cut, passed in July 2025, which the release calls a down payment. All of it has been allocated, the release says, and it is on track to be fully implemented by the end of 2028.
Taken together, the two would come to $62.6 billion. The new request is about four times the first tranche.
Congress set limits on how much of the $12.5 billion can go to each category of work, and the money cannot legally be moved from one workstream to another, the release says.
The FAA’s Modern Skies tracker shows how far that program has gone. Telecommunications replacement is furthest along, with 3,651 connections done. The release puts it at 70% of copper lines replaced with fiber, 5G wireless or low-earth-orbit links.
Radar is at the other end: 16 of 612 new radar systems have been deployed. Only five of 435 planned Enterprise Information Display Systems, which replace legacy floppy-drive systems, are in place.
Progress on the $12.5 billion program, 16 November 2026 (completed units; progress in %)
| Project | Done | Target | Progress |
|---|---|---|---|
| Telecommunications replaced | 3,651 | 5,170 | 71 |
| Surface Awareness Initiative installations | 143 | 220 | 65 |
| IP voice switches | 230 | 450 | 51 |
| Radio sites converted | 497 | 1,581 | 31 |
| Electronic flight strips | 28 | 89 | 31 |
| Tower simulation systems | 20 | 117 | 17 |
| Surface movement radars | 8 | 53 | 15 |
| New radar systems | 16 | 612 | 3 |
| Enterprise Information Display Systems | 5 | 435 | 1 |
Data as published on the FAA’s Modern Skies site, current as of 16 November 2026. The release gives lower counts for some items, for example 469 radio sites converted.
The FAA blames legacy equipment for Friday’s failure
The letter ties the request directly to the 13 November disruption. “Less than 24 hours later, the urgent need for this investment became undeniable when outdated, legacy equipment disrupted aircraft communications and radar feeds,” it says, referring to its earlier appeal to Congress.
The FAA’s account puts the start of the technical problem at about 20:30 GMT that Friday. Air traffic resumed at 01:15 GMT on Saturday, and the release describes the ground stop as lasting four hours.
Legacy equipment became unstable when data flooded the FAA’s FTI telecommunications network at a rate of 1,000 connection attempts every 4 to 5 seconds, the agency said. Its initial investigation points to two possible sources: a radar site in Amarillo, Texas, and a radio communications site in El Dorado, Arkansas, where its network provider L3Harris had been deploying a new router.
Instability began at 17 of the 22 Air Route Traffic Control Centers and spread into several Terminal Radar Approach Controls, which guide aircraft near major airports. About 3,500 aircraft landed safely.
Operators canceled about 12,462 flights that day, 9,082 of them by major airlines, though not all cancellations were directly caused by the ground stop. The agency reported no indication of a cyberattack.
The FAA blamed the legacy TDM system, older circuit-based telephone-line technology, and said none of the upgraded towers that received modifications from the $12.5 billion went down. It has disabled the function involved on the originating Juniper routers and on more than 60 others, and paused installing them. The FAA and L3Harris are still investigating the root cause.
Federal auditors counted 51 unsustainable systems in 2024
The state of the network was documented before Friday. A Government Accountability Office (GAO) report published in September 2024 described an FAA assessment carried out after a 2023 outage.
The assessment rated 51 of the FAA’s 138 air traffic control systems unsustainable.
That is 37% of the inventory. A further 54 systems, or 39%, were rated potentially unsustainable.
Of those 105 systems, 58 have critical operational impacts on the safety and efficiency of the national airspace, the report said.
As of May 2024, 17 systems were especially concerning. The investments meant to modernize them were not due for completion for at least six years.
Some were 10 to 13 years away. Four had no ongoing investment at all.
The report’s follow-up notes that the FAA responded with its Brand New Air Traffic Control System plan in May 2025, a three-year framework covering telecommunications, radar and voice communications. The watchdog still lists its priority recommendation on reporting to Congress as partially addressed.
For scale, a separate GAO report said the FAA had spent just over $14 billion on NextGen, its long-running modernization program, through fiscal year 2022. The new request alone is more than three times that.
In The Edge’s reading, the mix matters as much as the total. Four-fifths of the request is for buildings and airport grants, which take years to site and build, while cloud computing and telecommunications, the category of the network that failed on Friday, get $2 billion of it.
What to watch: the end of 2028, when the department expects the $12.5 billion program to be fully implemented.
Method: the request and its line items are from the joint letter of 17 November 2026 from the Secretary of Transportation, the FAA Administrator and the Director of the Office of Management and Budget, and the US Department of Transportation’s release of the same day; program progress is from the FAA’s Modern Skies site, data as of 16 November 2026; the account of the 13 November disruption is from the FAA’s questions and answers of 15 November 2026; system ratings are from GAO report GAO-24-107001 of 23 September 2024 and NextGen spending from GAO-24-105254 of 9 November 2023. Shares, sums, ratios and illustrative per-unit averages are The Edge’s calculations.
Sources: US Department of Transportation, Federal Aviation Administration, Office of Management and Budget, US Government Accountability Office, The Edge.