ACWA Power Closes $226 Million Financing for 300 MW Bash II Wind Farm in Uzbekistan
The Takeaway: Bash II sits in Uzbekistan’s Bukhara region, where ACWA Power’s project pages list three wind farms. The 21-year debt is limited-recourse: lenders look to the wind farm’s own cash flows, with ACWA’s support confined to a standby equity commitment and a reserve account. The Asian Development Bank, the Asian Infrastructure Investment Bank and Standard Chartered are among the lenders, and the filing gives no figure for the effect on ACWA’s results.
ACWA Power has reached financial close on the 300 MW Bash II wind farm in Uzbekistan’s Bukhara region, raising $226 million of long-term debt from a consortium of international lenders.
ACWA Power Company (Saudi Exchange: 2082) posted the announcement on the Saudi Exchange at 05:02 GMT on Sunday 15 November. It dates the funding to Friday 13 November and puts it at SAR 847.5 million. Financial close means the loan conditions are met and the money can be drawn.
The consortium includes the Asian Development Bank (ADB), the Asian Infrastructure Investment Bank (AIIB) and Standard Chartered Bank. The financing runs for 21 years, and the company lists no related parties to the transaction.
The agreements themselves were signed in May. In a release dated 7 May, ACWA said it had signed the financing agreements for Bash II with the same three lenders at the Asian Development Bank’s annual meeting, and that the debt covers more than two-thirds of the project’s total cost. The Saudi Exchange announcement of 15 November reports the financial close.
In the same release, ACWA said Bash II is backed by a 25-year power purchase agreement with the National Electric Grid of Uzbekistan and is expected to begin commercial operation in the second half of 2027. It placed the farm in the Gijduvan district of the Bukhara region, next to the Bash I wind farm.
Limited-recourse debt keeps ACWA’s exposure to two commitments
The loan is long-term, limited-recourse senior debt. Senior debt is repaid ahead of other claims on the project; limited recourse means lenders are repaid mainly from the wind farm’s own revenue rather than from its sponsor.
ACWA’s guarantees are confined to its standby equity commitment, a pledge to inject further equity if the project needs it, and a reserve account. The company describes those terms as market practice for limited-recourse renewable energy projects in Uzbekistan.
The money will fund the development, construction, ownership and operation of the plant. Measured against capacity, the debt comes to about $753,000 per megawatt.
The announcement does not give ACWA’s ownership share in the project, the tariff or an estimate of the financial impact on the company. Neither it nor the May release splits the $226 million between the three lenders.
AIIB’s May loan sets the shape of the lending
The National News Agency of Uzbekistan (UzA) carried a report on 6 May that the AIIB had signed a $107 million loan agreement with ACWA for the Bash 2 wind power plant, as the agency calls Bash II.
That report also said the project was co-financed by the ADB and Standard Chartered. In The Edge’s reading, if the AIIB’s May loan is unchanged, it would be 47.3% of the debt, leaving $119 million for the other lenders; the filing confirms neither figure.
Once running, Bash 2 is expected to generate about 943 gigawatt-hours of electricity a year, according to the same report. That would supply more than 336,000 households.
The same report put the carbon dioxide avoided at roughly 475,000 tons a year.
In The Edge’s reading, offered as an illustration rather than a figure either party reports, that expected output implies a capacity factor of about 35.9%, set against 300 MW running every hour of the year. The capacity factor is the share of the turbines’ maximum possible annual output that they actually deliver.
The agency described Bash 2 as building on the Bash 1 wind project and as part of a broader renewable energy cluster in the region. It said the project supports Uzbekistan’s goal of lifting renewables to 40% of its power mix by 2030.
The agency also reported that the AIIB and ACWA had built combined investments of about $440 million in Uzbekistan’s energy sector since 2019.
ACWA’s wind farms in the Bukhara region
ACWA’s own project pages list three wind farms in the Bukhara region: Bash, Dzhankeldy and Gijduvan. Bash and Dzhankeldy are 500 MW each, and each carries a 65% ACWA share.
Bash is listed at a project cost of $690 million and Dzhankeldy at $658 million. Both sell their output to the National Electric Grid of Uzbekistan, their sole offtaker, under 25-year power purchase agreements, on a build, own, operate and transfer basis.
Gijduvan, listed as the Gijduvan Wind IPP, is a 300 MW farm in the Gijduvan district, wholly owned by ACWA. With it, the three listed farms come to 1,300 MW.
ACWA’s project pages carry no entry under the Bash II name.
Across Uzbekistan, ACWA’s pages list ten projects with a published cost and capacity, from wind and solar farms to a gas-fired plant. Their combined project cost comes to $9.87 billion, and the table sets them out.
ACWA Power’s Uzbek projects (capacity in MW; cost in $ millions)
| Project | Capacity | Cost | Share |
|---|---|---|---|
| Bash wind | 500 | 690 | 65% |
| Dzhankeldy wind | 500 | 658 | 65% |
| Gijduvan wind | 300 | 403 | 100% |
| Karatau wind | 100 | 117 | 100% |
| Karakalpakstan wind | 1,500 | 1,550 | 100% |
| Kungrad 123 wind | 1,500 | 3,068.46 | 100% |
| Sazagan Solar 1 | 500 | 714 | 51% |
| Sazagan Solar 2 | 500 | 1,049 | 100% |
| Sirdarya gas plant | 1,500 | 1,093 | 51% |
| Riverside solar | 200 | 529 | 100% |
Capacity is generation only; the battery storage at Karakalpakstan, Kungrad 123, Sazagan Solar 1 and 2 and Riverside is excluded. Share is ACWA’s stake as its project pages print it. Bash, Dzhankeldy and Gijduvan are in the Bukhara region; Karatau, Karakalpakstan and Kungrad 123 in Karakalpakstan; Sazagan in Samarkand; Sirdarya in the Sirdarya region; Riverside in the Tashkent region. The Sirdarya page also gives a total investment value of $1.2 billion. A Beruniy wind farm is listed without a cost or share and is not shown.
Two of the listed projects carry dates. Karatau, which ACWA describes as Uzbekistan’s first publicly tendered wind project, shows commercial operation from the first quarter of 2025. Karakalpakstan shows a commercial operation date in the first quarter of 2027.
Bash II adds to a busy year of financings for the group. In its nine-month results release of 5 November, ACWA said four projects reached financial close in the period, at an aggregate investment cost of about SAR 19.2 billion.
What to watch: ACWA expects Bash II to begin commercial operation in the second half of 2027.
Method: financing terms and the financial close are from ACWA Power Company’s announcement on the Saudi Exchange of 15 November 2026; the May signing, the share of project cost, the power purchase agreement’s term, the expected start of commercial operation and the plant’s location are from ACWA’s release of 7 May 2026; project capacities, costs, shares and contract terms are from ACWA’s project pages as read on 16 November 2026, and group figures from its nine-month results release of 5 November 2026; the AIIB loan, expected output and household and emissions figures are from UzA’s report of 6 May 2026. Debt per megawatt, the share of debt, the capacity factor and the sums are The Edge’s calculations.
Sources: ACWA Power Company, Saudi Exchange, UzA, The Edge.