DP World Raises Maputo Port Investment to $200 Million, Targets 650,000 TEU by 2027
The Takeaway: DP World has raised its Maputo container terminal investment to $200 million and lifted its capacity goal to 650,000 TEU a year. Its statements last year and this week give different starting capacities for the terminal. The expansion is designed to take larger vessels at a port that handled a record 32.0 million tons in 2025, and a new weekly service from China is due to start calling there later this month.
Maputo’s container terminal is set to grow past its original plan, with its budget now $200 million and its annual capacity goal raised by 120,000 TEU.
DP World Lifts Both the Budget and the Target
DP World now plans to spend $200 million on the terminal, up from the $165 million it first committed. As recently as 2 November, it was still describing the work as a $165 million expansion.
Capacity is due to reach 650,000 twenty-foot equivalent units a year by the second quarter of 2027, the company said on Wednesday. TEU, as the unit is known, is the standard measure of container volume. The company added that the larger terminal will be able to take bigger vessels and work more efficiently.
The company’s statements differ on where the terminal starts. The one issued on 18 November counts from 225,000 TEU and says the project will nearly triple capacity. The one issued on 1 May 2025 listed current capacity as 255,000 TEU.
The latest statement does not address the difference. The target is 2.9 times the first figure and 2.5 times the second.
Maputo container terminal: the plan of May 2025 and the plan of November 2026
| Measure | May 2025 | Nov 2026 | Change |
|---|---|---|---|
| Investment ($ million) | 165 | 200 | +21.2% |
| Stated starting capacity (TEU a year) | 255,000 | 225,000 | Not aligned |
| Capacity target (TEU a year) | 530,000 | 650,000 | +22.6% |
Changes are calculated from the two plans. Each starting capacity is as printed in that statement.
The announcement followed a meeting between Essa Kazim, the Group Executive Chairman of DP World, and Daniel Chapo, President of Mozambique. They discussed expanding the company’s operations, further investment in trade infrastructure and transport links with neighboring markets.
Kazim said Mozambique has an opportunity to become “one of Southern Africa’s most important trade gateways.”
The Works Center on a Longer Quay and a Deeper Berth
The plan set out at the May 2025 ground-breaking was to lift capacity to 530,000 TEU. The budget is now $35 million higher and the target 120,000 TEU higher, and the company has not said what the extra money covers.
The works described in May 2025 more than double the quay to 650 meters. The berth is to be deepened to 16 meters, from 12. New ship-to-shore cranes, which move containers between vessel and quay, are also planned. Whether those specifications still stand is not stated in the latest release.
DP World’s note of 2 June 2025 on a meeting with President Chapo cited a commitment to double the port’s operational capacity within a year. The latest statement does not say how far that doubling has progressed. It dates the terminal’s 650,000 TEU target to the second quarter of 2027, within 26 months of the ground-breaking.
The Port Handled a Record Tonnage in 2025
DP World operates the container terminal and is a shareholder in the Maputo Port Development Company (MPDC), which holds the concession, the right to run and develop the port, until 2058. MPDC is a partnership between Caminhos de Ferro de Moçambique, the national railway company, and Portus Indico, a group made up of Grindrod, DP World and Mozambique Gestores.
A February 2024 addendum added 25 years to a term that had been due to end in 2033. The extension rested on a $2.06 billion investment plan.
That plan includes taking the container terminal to 1 million TEU a year. In The Edge’s reading, the higher target brings the terminal closer to that goal, at 65% of it, though the latest release does not link the two plans.
The whole port handled 32.0 million tons in 2025, an all-time high, MPDC said in January. That equals 86% of the 37 million tons of annual capacity cited in February 2024, and the comparison does not allow for any capacity added since.
Port of Maputo, 2024 and 2025
| Measure | 2024 | 2025 | Change |
|---|---|---|---|
| All terminals (million tons) | 30.9 | 32.0 | +3.4% |
| MPDC direct operations (million tons) | 14.2 | 15.2 | +6.4% |
| Concession fees paid to the state ($ million) | 46.8 | 48.9 | +4.5% |
Tonnage changes are MPDC’s published percentages and differ from changes on the rounded tonnages shown; the fee change is calculated.
Those fees have risen 17.3% in two years, from $41.7 million in 2023.
Shipping and Trade Links Are Widening Around the Port
DP World’s Shipping Solutions business plans to start the China Africa Link, a weekly service, later this month. It will run from Shanghai, Ningbo and Nansha through Port Klang to Dar es Salaam and Maputo, returning through Singapore.
Inland, the company runs a logistics hub at Komatipoort in South Africa. It said in November 2025 that Maputo was connected directly with Johannesburg, Eswatini and Zimbabwe, with daily trains to various destinations.
The announcement comes days after the UAE and Mozambique said on 14 November that they had concluded talks on a Comprehensive Economic Partnership Agreement, a broad deal covering trade and investment. The agreement still has to be signed and ratified.
Non-oil trade between the two countries reached $2.5 billion in the first nine months of 2026, up 49% on a year earlier, the Emirates News Agency (WAM) reported. During President Chapo’s visit to Abu Dhabi, his office said, Mozambique signed a cooperation agreement with the Abu Dhabi Fund for Development that provides for a $500 million loan.
For Mozambique, the terminal budget equals 0.8% of the $24.8 billion the International Monetary Fund projects for GDP this year, though the money is spread over the life of the project.
What to watch: The China Africa Link is scheduled to start in late November. Mozambique hosts its international investment conference in Maputo on 9 and 10 December. The terminal’s 650,000 TEU target falls due by the second quarter of 2027.
Method: percentage changes, capacity multiples and shares are The Edge’s calculations from DP World’s statements of 18 November 2026, 2 November 2026, 27 November 2025, 2 June 2025 and 1 May 2025, the Maputo Port Development Company’s statements of 13 January 2026, 21 January 2025 and 26 February 2024, the Emirates News Agency report of 14 November 2026, the Presidency of Mozambique’s statements of 14 November 2026, and the International Monetary Fund’s World Economic Outlook of October 2026.
Sources: DP World, Maputo Port Development Company, Presidency of the Republic of Mozambique, Emirates News Agency, International Monetary Fund, The Edge.